We want to be a porch light of hope in our community.
Building project
Learn more about the PVILLEYI GEM CENTER
Construction Phases
-
This phase will involve the demo of the old building and laying the foundation.
-
This phase will involve building structural aspects of the project.
-
This phase will be the finishing touches on our building project.
PVILLEYI Building project (PVILLEYI GEM CENTER)
Current progress
Current Phase:
Phase 3
Phase 3 Progress:
Projected grand opening will be late August 2026, with our Pilot season tentatively scheduled to begin on September 1st.
Important Community Information:
Please watch for volunteers in this area during construction and use caution when walking in red zones.
Project leadership
-

Mike Caulkins
PROJECT MANAGER
Mike Caulkins is the Jobsite Supervisor for J Larson Homes. He has always had an interest in construction and enjoys being on site with subcontractors to help and troubleshoot anything they may need. His experience, expertise, and connections in the construction field give him all the tools he needs to lead this project. Mike is a co-founder of PvilleYI and has served as a volunteer since day one.
Since beginning construction on the project, Mike has been onsite on Fridays and Saturdays managing the build, working with volunteers and professionals, and building with his own hands.
If you have questions for Mike or are interested in volunteering services during the project, you can contact him through us at info@pvilleyi.org
-

Jenna Wiegand, AIA
ARCHITECT
Jenna Wiegand graduated from Pleasantville High School in 2003. Always passionate about design, she pursued and achieved her goal of becoming an architect. Jenna has served as an advisor to our board of directors in the planning process and served as the architect of the project. Because of her contributions, Jenna was recognized for her work by the American Institute of Architects, Iowa Chapter’s (AIA Iowa), as a participant in the Citizen Architect Program. Her work was highlighted in IA Architect Magazine in Spring of 2024. Read it here (page 8): AIA Iowa recognizes members who advocate for the profession through community leadership.
Project History
Phase 2 COMPLETE
Phase 2 Progress:
6-7-25: Framing Begins
6-13-25: Framing Lower Level Continues
6-14-25: Framing Lower Level Continues
6-19-25: Floor Joists Scheduled to Arrive
6-20-25: Framing Continues
6-27-25: Framing Continues
7-11-25: Framing Continues
7-18-25: Framing Continues
7-25-25: Framing Continues
8-1-25: Framing Continues
8-15-25: Framing Continues
8-30-25: Framing Continues
9-6-25: Framing Continues
9-13-25: Trusses
9-21-25: Trusses
9-26-25:Sheeting
9-27-25: Sheeting
10-4-25: Roof Prep and Sheeting
10-11-25: Roof Prep and Sheeting
10-18-25: Mechanical Rough Ins
10-25-25: South Windows Installed, Curbs for Rooftop Units Installed
11-1-25: Mechanical Rough Ins
11-11-25: Roof Installation
11-12-25: Roof Installation
11-13-25: Window Frame Installation
11-17-25: Window Glass Installation
11-22-25: Temporary Door Installation
1-16-26: HVAC Rooftop Units Installed
1-31-26: Rooftop Work
2-2-26: Door Installation
Phase 1 COMPLETE
Phase 1 Progress:
4-28-25: Demolition Begins
5-1-25: Demolition is complete.
5-7-25: Foundation Prep Work
5-8-25: Foundation Work Begins
5-12-25: Foundation Footings
5-13-25: Foundation Walls
5-14-25: Continued Foundation Work
5-16-25: Groundwork
5-21-25:Groundwork
5-23-25:Backfill and Groundwork
5-31-25:Pour Concrete Floor

