PVILLEYI Building Project

Current progress

PVILLEYI Building project

Current progress

Current Phase:

Phase 2

Phase 2 Progress:

  • 6-7-25: Framing Begins

  • 6-13-25: Framing Lower Level Continues

  • 6-14-25: Framing Lower Level Continues

  • 6-19-25: Floor Joists Scheduled to Arrive

  • 6-20-25: Framing Continues

Phase 1 COMPLETE

Phase 1 Progress:

  • 4-28-25: Demolition Begins

  • 5-1-25: Demolition is complete.

  • 5-7-25: Foundation Prep Work

  • 5-8-25: Foundation Work Begins

  • 5-12-25: Foundation Footings

  • 5-13-25: Foundation Walls

  • 5-14-25: Continued Foundation Work

  • 5-16-25: Groundwork

  • 5-21-25: Groundwork

  • 5-23-25: Backfill and Groundwork

  • 5-31-25: Pour Concrete Floor

Phase 1 COMPLETE

Important Community Information:

A portion of Jefferson street will be closed for approximately three months during this phase. Avoid the area in red during this time.