
PVILLEYI Building Project
Current progress
PVILLEYI Building project
Current progress
Current Phase:
Phase 1
Phase Progress:
4-28-25: Demolition Begins
5-1-25: Demolition is complete.
5-7-25: Foundation Prep Work
5-8-25: Foundation Work Begins
5-12-25: Foundation Footings
5-13-25: Foundation Walls
5-14-25: Continued Foundation Work
5-16-25: Groundwork
5-21-25: Groundwork
5-23-25: Backfill and Groundwork
5-31-25: Pour Concrete Floor
Important Community Information:
A portion of Jefferson street will be closed for approximately three months during this phase. Avoid the area in red during this time.
Learn more about the project














