PVILLEYI Building Project
Current progress
PVILLEYI Building project
Current progress
Current Phase:
Phase 2
Phase 2 Progress:
6-7-25: Framing Begins
6-13-25: Framing Lower Level Continues
6-14-25: Framing Lower Level Continues
6-19-25: Floor Joists Scheduled to Arrive
6-20-25: Framing Continues
Phase 1 COMPLETE
Phase 1 Progress:
4-28-25: Demolition Begins
5-1-25: Demolition is complete.
5-7-25: Foundation Prep Work
5-8-25: Foundation Work Begins
5-12-25: Foundation Footings
5-13-25: Foundation Walls
5-14-25: Continued Foundation Work
5-16-25: Groundwork
5-21-25: Groundwork
5-23-25: Backfill and Groundwork
5-31-25: Pour Concrete Floor
Phase 1 COMPLETE
Important Community Information:
A portion of Jefferson street will be closed for approximately three months during this phase. Avoid the area in red during this time.