Building Project: Phase 1 Complete

PHASE 1 COMPLETE

Phase one of our building project began on April 4, 2025 and was completed on May 31, 2025. This process involved demolition and foundation.

Phase 1 Progress:

  • 4-28-25: Demolition Begins

  • 5-1-25: Demolition is complete.

  • 5-7-25: Foundation Prep Work

  • 5-8-25: Foundation Work Begins

  • 5-12-25: Foundation Footings

  • 5-13-25: Foundation Walls

  • 5-14-25: Continued Foundation Work

  • 5-16-25: Groundwork

  • 5-21-25: Groundwork

  • 5-23-25: Backfill and Groundwork

  • 5-31-25: Pour Concrete Floor