Building Project: Phase 1 Complete
PHASE 1 COMPLETE
Phase one of our building project began on April 4, 2025 and was completed on May 31, 2025. This process involved demolition and foundation.
Phase 1 Progress:
4-28-25: Demolition Begins
5-1-25: Demolition is complete.
5-7-25: Foundation Prep Work
5-8-25: Foundation Work Begins
5-12-25: Foundation Footings
5-13-25: Foundation Walls
5-14-25: Continued Foundation Work
5-16-25: Groundwork
5-21-25: Groundwork
5-23-25: Backfill and Groundwork
5-31-25: Pour Concrete Floor